Read more about the article July 7: Reaching 71m in the casing and first Basler shuttle to SFJ.
Julien mounting one section of Kovacs augers after another, to a total length of 15m. As these are too long for our tower, the full length has to be assembled down hole, with all of the drill team supporting from above by lowering the individual pieces on climbing ropes.

July 7: Reaching 71m in the casing and first Basler shuttle to SFJ.

Driller’s report: ‘Today was an epic day! We made more progress down hole than any other day before. In a final attempt to gather information from beyond the 56m blockage,…

Comments Off on July 7: Reaching 71m in the casing and first Basler shuttle to SFJ.